The development of Paddington New Yard forms part of the extensive Crossrail infrastructure project transforming the rail transport system across London. Located between the Westbourne Park Tube station and London Paddington station, Paddington New Yard contains both the Royal Oak Portal and Westbourne Park Crossrail worksites. Cordek were able to assist in providing a formwork solution for the construction of a new 8000m² elevated bus deck which will connect to Westbourne Park Bus Garage.
Cordek delivered a first class service when supplying their trough mould system. They provided a detailed layout scheme that allowed us to optimise reuse and achieve our strict deadline.
Project Scope
The structural design required long spans and this was achieved using ribbed concrete slabs with depths of 800mm and 1000mm. The slab design was further complicated by having skewed spans and falls in two directions. The contractor’s aim was to construct the deck slab in three phases over the course of 12 months.
The Solution
The contractor programmed the slab construction into more than ten slab pours split over the three phases. The Cordek Project Design Office then detailed a trough layout scheme which optimised the reuse of the trough moulds and achieved the phased programme. The flexibility of the trough moulds meant that the many one-off moulds required to achieve the skews and falls could be easily accommodated.
The Process
The re-usable trough moulds were manufactured by bonding a tough polypropylene skin onto a solid expanded polystyrene (EPS) core. The trough layout design requires a range of interlocking components; end units, standard units, make-up units and striker units to be manufactured which when assembled on site create the trough profiles and lengths required. Cordek provided detailed layout schedules and individually referenced units, supplied in phased deliveries to achieve the necessary pour sequence.
Summary
The ribbed concrete slab design achieved the long spans required and helped to reduce the volume of concrete and overall weight of the slab. The Cordek trough system of lightweight moulds allowed for easy manual handling in both installation and simple striking producing the desired concrete finish for this exposed application. Following construction, the EPS core of the trough moulds was recycled.
For international enquiries please contact Peter Blanchard
For enquiries in the Manchester or Liverpool
areas please contact James Provan